Question: 4. Develop the network diagram of this table, compute the critical path using the forward pass and the backward pass. Compute the slack and explain
4. Develop the network diagram of this table, compute the critical path using the forward pass and the backward pass. Compute the slack and explain the benfit of this diagram.
| Activity | Predecessor | Duration |
| A | -- | 5 |
| B | A | 3 |
| C | B | 4 |
| D | -- | 3 |
| E | D | 2 |
| F | D | 5 |
| G | B | 3 |
| H | E, F | 2 |
| I | G | 4 |
| J | H | 4 |
| K | J | 3 |
| L | C | 4 |
| M | L | 4 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts