Question: dependencies shown in Table 2 below. table [ [ ID , Description,Predecessor, table [ [ Duration ] , [ ( Days ) ]
dependencies shown in Table below.
tableIDDescription,Predecessor,tableDurationDaystableSlackSLASurvey,BSoils report,ACTraffic design,ADParking Lot Layout,AEApprove Design,B C DFLighting,EGDrainage,EHLandscape,EISignage,EJBid Proposal,F G H I,
Table : Activities in planning the training seminar, assume FS dependencies between all activities.
a pts Draw a PDM project network diagram for this project to perform critical path analysis and to better understand slack available within project activities
b pts Identify the critical path and project duration using ABC notation.
c pts Perform both Forward and Backward Pass to find the earliest start ES late start LS and slack SL for each of the activities. Place the data directly on your network diagram drawn in part a
d pts ANDalso insert the slack data in the appropriate column in Table above.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock