Question: dependencies shown in Table 2 below. table [ [ ID , Description,Predecessor, table [ [ Duration ] , [ ( Days ) ]

dependencies shown in Table 2 below.
\table[[ID,Description,Predecessor,\table[[Duration],[(Days)]],\table[[Slack],[(SL)]]],[A,Survey,-,5,],[B,Soils report,A,20,],[C,Traffic design,A,30,],[D,Parking Lot Layout,A,5,],[E,Approve Design,B, C, D,80,],[F,Lighting,E,15,],[G,Drainage,E,30,],[H,Landscape,E,25,],[I,Signage,E,15,],[J,Bid Proposal,F, G, H, I,10,]]
Table 2: Activities in planning the training seminar, assume FS dependencies between all activities.
(a)5 pts. Draw a PDM project network diagram for this project to perform critical path analysis and to better understand slack available within project activities
(b)2 pts. Identify the critical path and project duration using A-B-C notation.
(c)6 pts. Perform both Forward and Backward Pass to find the earliest start (ES), late start (LS), and slack (SL) for each of the activities. Place the data directly on your network diagram drawn in part a,
(d)2 pts. ANDalso insert the slack data in the appropriate column in Table 2, above.
 dependencies shown in Table 2 below. \table[[ID,Description,Predecessor,\table[[Duration],[(Days)]],\table[[Slack],[(SL)]]],[A,Survey,-,5,],[B,Soils report,A,20,],[C,Traffic design,A,30,],[D,Parking Lot Layout,A,5,],[E,Approve

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!