Question: 4. Devos inc has 4 teams (A, B, C, D) and 4 (1, 2, 3, 4) potential tasks. The total amount of days each employee

4. Devos inc has 4 teams (A, B, C, D) and 4 (1, 2, 3, 4) potential tasks. The total amount of days each employee would need to allocate to each job is as follows:

Potential Tasks

Team

1

2

3

4

A

28

33

21

35

B

41

43

23

37

C

48

28

33

42

D

49

27

43

46

Use Excel solver

Match the team the most efficient task. What is the total number of days that these projects will take to get worked on?