Question: 4. DRAW THE NETWORK FROM THE GANTT CHART BELOW. (40 points) A. FIND THE CRITICAL PATH AND THE CRITICAL ACTIVITIES. B. FIND THE NONCRITICAL ACTIVITIES.
4. DRAW THE NETWORK FROM THE GANTT CHART BELOW. (40 points)
A. FIND THE CRITICAL PATH AND THE CRITICAL ACTIVITIES.
B. FIND THE NONCRITICAL ACTIVITIES.
C. FIND ACTIVITIES WITH SLACK.
D. ON THE SECOND CHART, WHAT CHANGES TOOK PLACE IN EACH ACTIVITY AT THE 6TH DAY? AND ANY CHANGE IN THE PROJECT TIME?