Question: 4 . Estimate the yellow and all - red time interval ( also known as the change and clearance intervals, respectively ) required for an

4. Estimate the yellow and all-red time interval (also known as the change and clearance intervals, respectively) required for an intersection with a width of 25 feet and an approach speed of 35 mph