Question: 4 . For a network shown below, normal time, crash time, normal cost, crash cost are given in table. Contract the network by crashing it

4. For a network shown below, normal time, crash time, normal cost, crash cost are given in table. Contract the network by crashing it to optimum value and calculate optimum project cost. Indirect cost Rs 100/- per day.
Normal
Crash
Activity
Time in days
Cost in Rs
Time in days
Cost in Rs
1-2
3
300
2
400
2-3
6
480
4
520
2-4
7
2100
5
2500
2-5
8
400
6
600
3-4
4
320
3
360
4-5
5
500
4
520