Question: 5. Normal time, crash time, normal cost, crash cost is given in table. Contract the network by 10 crashing it to optimum value and calculate

5. Normal time, crash time, normal cost, crash

5. Normal time, crash time, normal cost, crash cost is given in table. Contract the network by 10 crashing it to optimum value and calculate optimum project cost. Indirect cost = Rs 100/- per day. Activity 1-2 2-3 2-4 2-5 3-4 4-5 Normal Time Days) 3 6 S 4 5 Normal Cost (Rs) 600 480 2100 400 320 500 Crash Time (Days) 2 4 B 6 3 4 Crash Cost (Rs.) 400 520 2500 600 360 520

Step by Step Solution

There are 3 Steps involved in it