4. For a project with the following activities
Activity Duration Predecessor Free Float Total Float
Start 0--
A 8 Start
B 10 Start
C 3 A
D 7 A
E 6 C, B
F 7 C, B
G 5 D, E
H 3 F
End 0 G,H
a) Develop both AON and AOA networks below