Question: The project management team has gathered information necessary to develop a project network: predecessor activities, and activity time in days. The outcome of this meeting

The project management team has gathered information necessary to develop a project network: predecessor activities, and activity time in days. The outcome of this meeting are found in the following table:

Activity Duration Predecessor
A 5 START
B 8 A
C 3 B
D 4 A
E 5 C
F 7 C
G 6 D, E
H 8 F
I 6 G
J 5 H

Based on the provided information in the table:

1. Prepare a project network diagram

2. Indicate free float and total float for each activity

3. Calculate and identify the critical path

4. Determine the project duration

5. Prepare a Gantt chart showing the project schedule (assume a start date of Jan 1, 2019)

The assignment is divided as follows:

Sequencing of activities and network diagram (30 marks)

Float calculations (20 marks)

Identification of critical path (10 mark)

Calculation of project duration (10 mark)

Completeness of Gantt chart (30 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!