Question: The project management team has gathered information necessary to develop a project network: predecessor activities, and activity time in days. The outcome of this meeting
The project management team has gathered information necessary to develop a project network: predecessor activities, and activity time in days. The outcome of this meeting are found in the following table:
| Activity | Duration | Predecessor |
| A | 5 | START |
| B | 8 | A |
| C | 3 | B |
| D | 4 | A |
| E | 5 | C |
| F | 7 | C |
| G | 6 | D, E |
| H | 8 | F |
| I | 6 | G |
| J | 5 | H |
Based on the provided information in the table:
1. Prepare a project network diagram
2. Indicate free float and total float for each activity
3. Calculate and identify the critical path
4. Determine the project duration
5. Prepare a Gantt chart showing the project schedule (assume a start date of Jan 1, 2019)
The assignment is divided as follows:
Sequencing of activities and network diagram (30 marks)
Float calculations (20 marks)
Identification of critical path (10 mark)
Calculation of project duration (10 mark)
Completeness of Gantt chart (30 marks)