Question: 4) For the following project, draw the node network, perform the CPM calculations, mark the critical path, and complete the table (you don't need to
4) For the following project, draw the node network, perform the CPM calculations, mark the critical path, and complete the table (you don't need to fill this table in if you explicitly provide the information in your network). If the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero