Question: 4. Given the following task information, shown in the table below: a. Create the network diagram b. Find the indices for each task: ES, EF,

4. Given the following task information, shown in

4. Given the following task information, shown in the table below: a. Create the network diagram b. Find the indices for each task: ES, EF, LS, and LF C. Determine the critical time for the project d. Determine the critical path e. Calculate the slack time for each task Task Predecessor(s) Duration (weeks) 4 A B 6 10 D 9 3 E F 2 A,B B,C D DE E G 1 5