Question: Given the information in the following table: Activity Duration Predecessors a 4 None b 5 None c 5 a d 6 a e 5 b,c
Given the information in the following table:
| Activity | Duration | Predecessors |
| a | 4 | None |
| b | 5 | None |
| c | 5 | a |
| d | 6 | a |
| e | 5 | b,c |
| f | 4 | d |
| g | 5 | e |
Construct the network diagram
Find each activity's ES, EF, LS, and LF.
Identify all paths. Which path is the critical path?
How long will it take to complete the project?