Question: _____ 4. In JIT and Lean, production does not take start until there is demand for it. This is called: A) the pull method B)
_____ 4. In JIT and Lean, production does not take start until there is demand for it. This is called:
A) the pull method
B) the push-pull method
C) the continuous improvement method
D) none of the above
_____ 5) The ________ is the sequence of activities between a project's start and finish that takes the longest time to complete.
A) the path using the optimistic times
B) the path using the most likely times
C) the critical path
D) none of the above
_____ 6). Which one of the following statements concerning the economic order quantity (EOQ) model is TRUE?
A) An increase in the holding cost per unit will increase the EOQ
B) A decrease in ordering cost (S) will decrease the EOQ
C) A decrease in demand will increase the EOQ
D) None of the above is true
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
