Question: 4 of 5 . . . table [ [ Activity , Preceding,Duration ] , [ A , - , 9 ] , [ B

4 of 5
...
\table[[Activity,Preceding,Duration],[A,-,9],[B,A,2],[C,A,12],[D,A,5],[E,B,6],[F,C, F,8],[H,D,3],[I,H,8],[J,E, I,6],[K,E,,2]]
4.1 Based on the information provided in the table, which activities should the project manager identify as critical?
4.2 How much slack exists for activities A and F?
4.3 How long will it take for the Gautrain project to be completed?
 4 of 5 ... \table[[Activity,Preceding,Duration],[A,-,9],[B,A,2],[C,A,12],[D,A,5],[E,B,6],[F,C, F,8],[H,D,3],[I,H,8],[J,E, I,6],[K,E,,2]] 4.1 Based on the