Question: Consider the following table, Activity Preceding Duration A -- 6 B -- 4 C A 8 D A, B 5 E C 4 F D
Consider the following table,
| Activity | Preceding | Duration |
| A | -- | 6 |
| B | -- | 4 |
| C | A | 8 |
| D | A, B | 5 |
| E | C | 4 |
| F | D | 4 |
a) Draw the Network diagram
b) Calculate the critical path and expected duration