Question: ( 4 ) Perform a project management analysis for the data given below to determine ES , EF , LS , LF , and slack

(4) Perform a project management analysis for the data given below to determine ES, EF, LS, LF, and slack for each activity, the total project completion time, and the critical path.
\table[[Activity,Time (weeks),Predecessors,Activity,Time (weeks),Predecessors],[A,5,-,E,3,B],[B,4,-,F,5,B],[C,1,A,G,9,D, E],[D,2,A,H,6,C, F]]
(a) Draw a network with t,ES,EF,LS, and LF(follow the same format as Figure 11.5 on p.394).
(b) Complete the following table (similar in format to Table 11.3 on p.396).
\table[[Activity,Time (weeks),ES,EF,LS,LF,Slack,Critical?],[A,,,,,,,],[B,,,,,,,],[C,,,,,,,],[D,,,,,,,],[E,,,,,,,],[F,,,,,,,],[G,,,,,,,],[H,,,,,,,]]
(c) Identify the critical path(s):
(d) Based on your analysis, the project completion time is: weeks and the least critical activity is:
 (4) Perform a project management analysis for the data given below

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!