Question: ( 4 ) Perform a project management analysis for the data given below to determine ES , EF , LS , LF , and slack
Perform a project management analysis for the data given below to determine ES EF LS LF and slack for each activity, the total project completion time, and the critical path.
tableActivityTime weeksPredecessors,Activity,Time weeksPredecessorsAEBBFBCAGD EDAHC F
a Draw a network with and follow the same format as Figure on p
b Complete the following table similar in format to Table on p
tableActivityTime weeksESEFLSLFSlack,Critical?ABCDEFGH
c Identify the critical paths:
d Based on your analysis, the project completion time is: weeks and the least critical activity is: