Question: (4 Points) Given the following data, how would you schedule the jobs applying Johnsons Rule? What is your resulting makespan? Job M1 M2 (Processing Time

(4 Points) Given the following data, how would you schedule the jobs applying Johnsons Rule? What is your resulting makespan? Job M1 M2 (Processing Time at Machines 1 and 2) A 5 2 B 5 4 C 7 5 D 7 7 E 6 7 F 3 4