Question: 7. (4 Points) Given the following data, how would you schedule the jobs applying Johnson's Rule? What is your resulting makespan? (Processing Time at Machines

7. (4 Points) Given the following data, how would

7. (4 Points) Given the following data, how would you schedule the jobs applying Johnson's Rule? What is your resulting makespan? (Processing Time at Machines 1 and 2) Job A B D E F M1 5 5 7 7 6 3 M2 2 4 5 7 7 4