Question: 4 Problem 2 1 - 1 8 ( Algo ) oints Product A is an end item and is made from two units of B
Problem Algo
oints
Product is an end item and is made from two units of and four of is made of two units of and two of is made of two units of and two of
Skipped
A has a lead time of one week. B C and E have lead times of two weeks, and D and F have lead times of three weeks.
If units of A are required in Week develop the MRP planning schedule; specifying when items are to be ordered and received. There are currently no units of inventory on hand. Leave no cells blank be certain to enter wherever required.
References
tablePeriod,Gross requirements,,,,,,,,,,Item AScheduled receipts,,,,,,,,,,Projected available balance,,,,,,,,,,Net requirements,,,,,,,,,,Planned order receipts,,,,,,,,,,Planned order releases,,,,,,,,,,Gross requirements,,,,,,,,,,Item BScheduled receipts,,,,,,,,,,Projected available balance,,,,,,,,,,Net requirements,,,,,,,,,,Planned order receipts,,,,,,,,,,Planned order releases,,,,,,,,,,Gross requirements,,,,,,,,,,Item CScheduled receipts,,,,,,,,,,Projected available balance,,,,,,,,,,Net requirements,,,,,,,,,,Planned order receipts,,,,,,,,,,Planned order releases,,,,,,,,,,Gross requirements,,,,,,,,,,Item DScheduled receipts,,,,,,,,,,Projected available balance,,,,,,,,,,Net requirements,,,,,,,,,,Planned order receipts,,,,,,,,,,LAL,Planned order releases,,,,,,,,,,Gross requirements,,,,,,,,,,Item Scheduled receipts,,,,,,,,,,Projected avaliable balance,,,,,,,,,,Net requirements,,,,,,,,,,Planned order receipts,,,,,,,,,,Planned order releases,,,,,,,,,,Gross requirements,,,,,,,,,,Item FScheduled receipts,,,,,,,,,,Projected available balance,,,,,,,,,,Net requirements,,,,,,,,,,Planned order receipts,,,,,,,,,,Planned order releases,,,,,,,,,,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock