Question: 4 pts PROJECT CRASHING PROBLEM ( all time in Days, all cost in $ ) : What is the Normal Duration of the project?

4 pts
PROJECT CRASHING PROBLEM (all time in Days, all cost in $): What is the Normal Duration of the project?
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Normal],[Time]],\table[[Crash],[Time]],\table[[Normal],[Cost]],\table[[Crash],[Cost]]],[A,-,5,4,1000,1400],[B,-,3,3,800,-],[C,A,B,3,1,600,900],[D,B,4,2,1600,2000],[E,C,D,5,3,800,1200],[F,E,2,1,1300,1400]]
12
15
13
16
14
 4 pts PROJECT CRASHING PROBLEM (all time in Days, all cost