Question: Question 57 5 p PROJECT CRASHING PROBLEM (all time in Days, all Cost in $): What is the total crashing cost to crash the project

Question 57 5 p PROJECT CRASHING PROBLEM (all
Question 57 5 p PROJECT CRASHING PROBLEM (all time in Days, all Cost in $): What is the total crashing cost to crash the project by 4 days? Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A 5 4 1000 1400 B 3 3 800 A.B 3 1 600 900 U o B 4. 2 1600 2000 1200 CD 5 3 800 E F E 2 2 1 1300 1400 $700 O $800 O $650 $750 $600