Question: 4 . The Contractor submitted the programme on 3 January. On 1 6 January, a routine progress meeting took place in the headquarter office of
The Contractor submitted the programme on January. On January, a routine progress meeting took place in the headquarter office of the Project Manager. The Contractor and the Project Manager discussed the issues in the submitted programme. On January, the Contractor received no response from the Project Manager and the Contractor notified the Project Manager of this. On January, the Project Manager has still not responded, and he emailed the Contractor saying he disagreed with some of the matters in the programme especially the delay foreseen in the programme. The Project Manager did not give further elaboration or reasons.
What is the status of the programme submitted on January?
It is accepted because the Project Managers failure to respond to the Contractors notification means the programme is treated as accepted;
It is accepted if the Contractor has also notified an early warning on the matter under clause ;
It is accepted because the Project Managers failure to notify acceptance or nonacceptance within one week of the Contractors notification and the programme is treated as accepted by the Project Manager.
It is not accepted because the Project Manager has further two weeks to respond following the receipt of the Contractors notification of failure;
It is not accepted because the Project Manager clearly states that he disagrees with the programme and it is the Contractors obligation to submit a revised programme according to Cl to satisfy the Project Managers comments.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock