Question: 4. The diagram below represents a gear production process. Station 1 takes 3 minutes to mill a metal blank. Station 2 then takes 8 minutes

4. The diagram below represents a gear production process. Station 1 takes 3 minutes to mill a metal blank. Station 2 then takes 8 minutes to grind teeth into the gear. The production facility is open for 8 hours per day and has a policy that there be no WIP at the end of the day. Calculate the total average flow time for the process. Show your work on the steps needed to calculate this. (10 pts)