Question: 4 . The table below shows the estimate for a project in which you have been assigned the project manager ( PM ) . The
The table below shows the estimate for a project in which you have been assigned the project manager PM The previous PM was in the process of developing the cost estimate when she was promoted and asked to lead a more complex project. You were asked to take over and you jumped at it the opportunity to lead your first project. Your next deliverable as the new PM is to complete the cost estimate below. When completing the cost estimate youre expected to make some reasonable assumptions since you dont have all the facts. points The table below shows the estimate for a project in which you have been assigned the project manager PM The previous PM was in the process of developing the cost estimate when she was promoted and asked to lead a more complex project. You were asked to take over and you jumped at it the opportunity to lead your first project. Your next deliverable as the new PM is to complete the cost estimate below. When completing the cost estimate you're expected to make some reasonable assumptions since you don't have all the facts. points
a What is your cost of testing? Note you can make any assumption but clearly state the assumption. points
b What is the total amount estimated for the flexible account? points
tabletableLevelItemItem,UnitHrsUnit Cost,Total,tableCalculate ofcost allocatedto each levelitemPMPMProject teams,membersHardware,,,,Equipment TEquipment TtabletableSoftwareDevelopmentTesting,,,?,tableFlexible accountbuffer Allocatedto traveling, training, Team skilldevelopment administration, andmeeting
aWhat is your cost of testing? Note you can make any assumption but clearly state the assumption. points
bWhat is the total amount estimated for the flexible account? points
Level Item Item UnitHrs Unit Cost Total Calculate of cost allocated to each level item
PM
PM
Project teams
members
Hardware
Equipment T
Equipment T
Software
Development
Testing
Flexible accountbuffer Allocated to traveling, training, Team skill development, administration and meeting
Total Project Cost
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock