Question: 4. You have prepared the project information that is given below: Activity Predecessor Normal Time Normal Cost Crash Cost Crash Time 30 40 40 70

4. You have prepared the project information that is given below: Activity Predecessor Normal Time Normal Cost Crash Cost Crash Time 30 40 40 70 - - N - A 30 60 A 10 20 50 ammana 50 80 60 90 - W V D. E. F 50 70 What is the normal critical path? - What is the normal project duration? - What is the normal project cost
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock