Question: I need someone to help solve this question using Solver in Excel and show the steps ( visual ) in details via Excel.. Question -

I need someone to help solve this question using Solver in Excel and show the steps (visual) in details via Excel.. Question- Given the following project (all times are in days):
Activity
Predecessor
Normal
Time
Normal
Cost
Crash
Time
Crash
Cost
a 5 $503 $150
b 4402200
c b 7706160
d a, c 220150
e a, c 330
f b 8805290
g d 5504100
h e, f 6603180(a) Draw the network (AOA or AON) and fi nd the
critical path, time, and cost for an all - normal
level of project activity.
(b) Calculate the crash cost - per - day (all activities
may be partially crashed).
(c) Find the optimal way of getting an 18- day delivery time. What is the project cost?
(d) Find the optimal way of getting a 16- day delivery time. What is the project cost?
(e) Calculate the shortest delivery time for the
project. What is the cost?
(f) Repeat questions (c),(d), and (e) using Excel. A picture of the table that has been worked on nd a diagram showing the AON is also attached. \table[[Activity,\table[[Prede-],[cessors]],\table[[Normal],[Duration]],\table[[Crash],[Duration]],Normal Cost,Crash Cost,Cost per Day,Activity,\table[[Actual],[Duration]],Actual Cost],[a,-,5,3,$50,$150,$50,a,5,$50
 I need someone to help solve this question using Solver in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!