Question: 40) Splitting activities refers to: (1mark) A) Assigning the work to two or more workers. B) Assigning the work to two or more days. C)
40) Splitting activities refers to: (1mark) A) Assigning the work to two or more workers. B) Assigning the work to two or more days. C) Starting an activity, interrupting it to use a resource elsewhere, and then returning to work on the activity. D) Breaking each non-critical activity into two or more components and subdividing the resources they use by a similar divisor. 41) The first step in the control cycle is: (1mark) A) Setting a goal. B) Measuring progress. C) Comparing actual with planned performance. D) Taking action. 42) The classic project S-curve is a plot of: (1mark) A) Labor hours versus money expended. B) Money expended versus elapsed time. C) Elapsed time versus labor hours. D) Number of personnel versus days behind schedule