Question: 4.4. Complete the following table. Lead time for the part is 1 week, and the order quantity is 150. What action should be taken? 1

4.4. Complete the following table. Lead time for
4.4. Complete the following table. Lead time for the part is 1 week, and the order quantity is 150. What action should be taken? 1 2 2 3 4 70 100 120 80 80 Gross Requirements Projected Available Net Requirements Planned Order Receipt Planned Order Release Answer. Orders for 150 parts should be released in week 1 and 2 separately