Question: 5 0 . A project manager is quantifying risk for her project. Several of her experts are offsite but wish to be included. How can

50.A project manager is quantifying risk for her project. Several of her experts are offsite but wish to be included. How can this be done?
(2 Points)
Do a Monte Carlo analysis using the internet as a tool
Apply the critical path method
Determine options for recommended corrective action
Apply the Delphi Technique
51.During which risk management process is a determination to transfer a risk made?
(2 Points)
Identify risks
Perform Quantitative Risk Analysis
Plan Risk Response
Monitor and Control Risks