Question: A project manager is quantifying risk for her project. Several of her experts are off-site, but wish to be included. How can this be done?
A project manager is quantifying risk for her project. Several of her experts are off-site, but wish to be included. How can this be done? A. Use Monte Carlo analysis using the Internet as a tool. B. Apply the critical path method. C. Determine options for recommended corrective action. D. Use the Delphi technique.