Question: ( 5 0 points ) You ve been given the following information about the Project Delta. The project started on September 2 , 2 0
points Youve been given the following information about the Project Delta. The project started on September and the project manager asks you for help on assessing its ongoing progress as completed through September the current date by doing the following tasks. For submission, attach the completed MS Project and submit via Canvas upload.
ActivityDuration Predecessors Resource complete
A Research product Tom Allen
B Interview customers ALiz Watts
C Design survey A Rich Watkins
D Collect data B C Gary Sims
Now, suppose we assign costs to each of the resources in the following amounts.
Resource Cost
Tom Allen $hour
Liz Watts $hour
Rich Watkins $hour
Gary Sims $hour
Using the above project data, enter the various tasks and create a Gantt chart using MS Project. Assign the individuals responsible for each activity and enter the resource cost rate data into the project. Dont forget to save the baseline!
Create the Cash flow statement for the project baseline. What is the planned project budget per task?
Once you have completed the Baseline, update the project information with the percentage complete tool. What does the tracking Gantt Chart look like?
Originally, the human resources costs are the only planned expenditures. However, in carrying out Task A research product, a total of $ extra cost was incurred to purchase some research tools. Use MS Project to create an Earned Value report of the most recent project status. Activity Duration
A Research product
B Interview customers
C Design survey
A
B C
Tom Allen
Liz Watts
Rich Watkins
Gary Sims
Now, suppose we assign costs to each of the resources in the following amounts.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock