Question: Given the following information regarding a project: Activity Duration Predecessors a 2 None b 3 None c 2 a d 4 a , b e

Given the following information regarding a project:
Activity Duration Predecessors
a 2 None
b 3 None
c 2 a
d 4 a, b
e 4 c
f 3 c
g 5 d, e
h 2 f, g
Which of the following is NOT a path in the network?
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-h
1 points
QUESTION 8
What is the critical path?
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-g
1 points
QUESTION 9
How long will it take to complete the project?
4
9
10
13
15
1 points
QUESTION 10
What is the LS for activity a?
0
1
3
4
5
1 points
QUESTION 11
What is the LF for activity f?
10
13
15
19
1 points
QUESTION 12
What is the EF for activity g?
7
8
10
13
15
1 points
QUESTION 13
What is the LF for activity h?
7
8
10
13
15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!