Question: 5. (20 points) Use critical path method to manage the following project: Activity Duration Immediate Predecessors A 12 B 8 A 4 A D 3

5. (20 points) Use critical path method to manage

5. (20 points) Use critical path method to manage the following project: Activity Duration Immediate Predecessors A 12 B 8 A 4 A D 3 A E 12 B F 18 G 5 H 4 E, F I 9 D, G J 6 HI (a) (5 points) Draw the network. (Try on scratch papers first, and draw a neat network as your final answer. Dummy arrow isn't needed for this question.) (b) (3 points) What is the total completion time? (c) (10 points) Write down the total float/slack for each activity. (d) (2 points) What is the critical path