Question: 3. (20 points) Use critical path method to manage the following project: Activity Duration Immediate Predecessors A 6 B 8 A 12 A D 5

3. (20 points) Use critical path method to manage

3. (20 points) Use critical path method to manage the following project: Activity Duration Immediate Predecessors A 6 B 8 A 12 A D 5 A E 2 B F 8 C, E G 3 CE H 4 F I F J 6 D G K 2 I, J 6 (a) (5 points) Draw the network. (Try on scratch papers first, and draw a neat network as your final answer. Dummy arrow isn't needed for this question.) (b) (2 points) What is the total completion time? (c) (11 points) Write down the total float/slack for each activity. (d) (2 points) What is the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!