Question: 5 (2.5 points) In the critical path method, the ______ for an activity is the time between its earliest and latest start time or between
5 (2.5 points) In the critical path method, the ______ for an activity is the time between its earliest and latest start time or between its earliest and latest finish time. Question 5 options: slack time schedule buffer time labor time