Question: In the critical path method, the _ _ _ _ _ _ for an activity is the time between its earliest and latest start time

In the critical path method, the ______ for an activity is the time between its earliest and latest start time or between its earliest and latest finish time.
Group of answer choices
slack time
schedule
labor time
buffer time