Question: 5. a. Given the project network and baseline information below. Create a phase time-phased budget for the project. (6 marks) LEGEND ES DEF SL SL

5. a. Given the project network and baseline5. a. Given the project network and baseline5. a. Given the project network and baseline5. a. Given the project network and baseline

5. a. Given the project network and baseline information below. Create a phase time-phased budget for the project. (6 marks) LEGEND ES DEF SL SL LS DUR LF 2 B 8 0 0 2 6 8 8 D 12 0 0 8 4 12 0 A 2 0 0 2 2 2 | 12 F 15 0 0 123 15 20 7 2 7 E 10 22 2 4 5 9 9 3 12 Cost Per Week (Rands) A 200 B 200 C 200 200 600 600 200 500 600 100 200 300 400 D 400 | | E 400 300 200 400 400 100 400 200 300