Question: 5) A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the minimum total

5) A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the minimum total cost for completing this project as quickly as possible? (i.e crash to as short as possible but do not crash paths that do not shorten the overall project)

Activity

Predecessor

Normal Time

Normal Cost

Crash Time

Crashed Cost

A

--

8

$12,000

5

$22,000

B

A

12

$18,000

9

$32,000

C

A

15

$22,000

9

$62,000

D

B

3

$9,000

2

$18,000

E

C

9

$15,000

5

$35,000

F

E

7

$5,000

5

$8,000

G

D

8

$13,000

6

$23,000

H

A

12

$20,000

8

$32,000

J

H

6

$45,000

4

$56,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!