Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $5,000
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks. What is the lowest total cost for completing this project?

$222,667$217,000$222,000$208,000