Question: 5. A project's current total Earned Value (EV) is 150,000 and the Actual Cost (AC) is 100,000. What is the Cost Variance (CV) of the
5. A project's current total Earned Value (EV) is 150,000 and the Actual Cost (AC) is 100,000. What is the Cost Variance (CV) of the project? CV is 1.5 CV is -1.5 CV is 50,000 CV = -50,000
6. A project is estimated to cost 50,000 with a timeline of 50 days. After 25 days, the project manager finds that actual cost is 50,000. What is the Cost Performance Index (CPI)? CPI is 1 CPI is 1.5 CPI is 2 CPI is 0.5
7. What is EAC for the project if BAC = 50,000AC=10,000 EV = 7,000, ETC=50,000 $50,000 $67,000 $73,000 $60,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
