Question: A project's current total Earned Value (EV) is 150,000 and the Actual Cost (AC) is 100,000. What is the Cost Variance (CV) of the project?

A project's current total Earned Value (EV) is 150,000and the Actual Cost (AC) is 100,000. What is the Cost Variance (CV) of the project?
A project is estimated to cost 50,000 with a timeline of50 days. After 25 days, the project manager finds thatactual cost is 50,000. What is the Cost Performance Index (CPI)?
7. What is EAC for the project if BAC = 50,000AC=10,000 EV = 7,000, ETC=50,000

What is the best way to calculate the Estimate AtCompletion (EAC) when original estimates are no longer valid.
Compute SPI, CPI Estimate At Completion (EAC) and Variance At Completion (VAC) if both SPI and CPI influence the project work when given variables are

Budget At Completion (BAC) = $40,000

Earned Value (EV) = $26,000

Planned Value (PV) = $20,000

Actual Cost (AC) = $25,000

You are the project manager on a project that has $500,000 software development effort. There are two teams of programmers that will work for six month for a total of 8,000 hours. According to the project schedule your team should be done with 48% of the work. As of today, the project is 30% complete while 60% budget has been used. Calculate and share your conclusion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!