Question: 5. An activity-on-node diagram is shown below. The activity names and durations are shown above each activity Times are in weeks. (18 points for entire

5. An activity-on-node diagram is shown below.
5. An activity-on-node diagram is shown below. The activity names and durations are shown above each activity Times are in weeks. (18 points for entire problem.) a) Compute ES, EF, LS, and LF for each activity. Put cach number in the right place in the diagram. (12 points) The format is ES EF LS LF b) Compute slack for each activity. You can make a slack table, or write the slack under each activity. (4 points) c) What is the critical path? (1 point) d) What is the project duration? (1 point)