Question: 5. Calculate the total Project Cost for the given project if the project has to be finished 2 days earlier than previous plan End Start

5. Calculate the total Project Cost for the given

5. Calculate the total Project Cost for the given project if the project has to be finished 2 days earlier than previous plan End Start B Activity B D E Normal Duration 5 4 6 7 7 Crash Duration 4 2 5 4 5 Normal Cost(Rs) 4000 3000 2200 5000 3000 Crash Cost (Rs) 6000 4000 3000 8000 6000