Question: QUESTION 4 As project manager, you decide to split the project to several modules as shown in Table 2. Your plan is to reduce the

QUESTION 4 As project manager, you decide to

QUESTION 4 As project manager, you decide to split the project to several modules as shown in Table 2. Your plan is to reduce the project duration by maximum crashing for Module A. Your indirect cost is RM 100/ day. Calculate your total project cost for Module A based on Table 2. Activity Normal Pred Duration (ND) Day A 5 Crash Duration (CD) days Normal Cost (NC) RM Crash Cost (CC) RM 3 350 450 B 4 A 3 400 500 6 A 3 450 900 D 3 B.C 2 400 470 Table 2 Cost Duration (Module A)