Question: 5 Compute the IRR statistic for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final
5 Compute the IRR statistic for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Projects Time cash flow 0 -$2,000 5750 $780 3 $720 $500 $300 20 IRR References Should the project be accepted or rejected? accepted Orejected