Question: 5. Consider the following project. O Task Description Marks-06 Duration (Weeks) 6 Immediate Predecessors 15 B A 25 B D 16 B E Require Analysis

5. Consider the following project. O Task

5. Consider the following project. O Task Description Marks-06 Duration (Weeks) 6 Immediate Predecessors 15 B A 25 B D 16 B E Require Analysis System Design Programming Telecoms Hardware Installation Integration System Testing Training Support Handover and Go-Live 30 B F 10 C D EF 10 G H 1 5 G 5 H a. Draw a project network b. What are the critical activities? c. Develop the activity schedule for the project d. What activity has the most slack time