Question: 5. Given the following network project with multiple time estimates in weeks: Activity Optimistic Modal Pessimistic IP 10 14 16 12 12 12 MOGOT D

 5. Given the following network project with multiple time estimates in

5. Given the following network project with multiple time estimates in weeks: Activity Optimistic Modal Pessimistic IP 10 14 16 12 12 12 MOGOT D 10 12 A 8 9 B 10 12 14 C. D a. What is the expected project completion time? b. Identify the critical path(S). C. Describe each of the task distributions as either skewed right, skewed left, normal, or cor d. What is the probability that the project will exceed 32 weeks? e. What is the probability that the project can be completed within 34 weeks