Question: Using the table in problem 3.17, answer the following questions: 3.17 Bill Fennema, president of Fennema Construction, has developed the tasks, durations, and predecessor relationships

Using the table in problem 3.17, answer the

Using the table in problem 3.17, answer the following questions: 3.17 Bill Fennema, president of Fennema Construction, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow. Immediate Predecessor(s) Activity A - 24 A A A B E, C E, C F F D, G, H I, J Time Estimates (in weeks) Most Optimistic Likely Pessimistic 4 8 10 2 8 8 12 16 4 6 10 1 2 3 6 8 20 2 3 4 2 6 6 4 6 12 2 2 3 H I J K a) Determine the expected time for each activity. b) Determine the variance and standard deviation for each activity. c) Using the critical path A- CFH-JK, determine the expected completion time for the project d) Determine the variance and standard deviation for the project. e) What is the probability of completing the project in less than 40 weeks? f) What is the probability of completion of the project before week 36

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!