Question: [ 5 ] Material requirements planning ( MRP ) is used to plan and control material requirements. The master production schedule ( MPS ) for

[5]
Material requirements planning (MRP) is used to plan and control material requirements. The master production schedule (MPS) for three sizes of screwdrivers is given in the table. All three screwdrivers (4mm,6mm and Star 8) use the same handle. The MPS requirements are:
The inventory record (item master file) shows the following planning factors: batches are set at quantities of 20 ; safety stock is set at 2 handles; the available inventory is 70 and the lead time for orders is two weeks.
4.1 In which week will the first order be issued?
4.2 In which week will the second order be issued?
4.3 What will the available inventory be in week 3?
4.4 What will the available inventory be in week 5?
4.5 How many items are included in the safety stock to begin with?
\table[[,Week 0,Week 1,Week 2,Week 3,Week 4,Week 5],[\table[[Gross],[required]],,,,,,],[\table[[Available],[inventory]],,,,,,],[\table[[Planned],[order]],,,,,,]]
 [5] Material requirements planning (MRP) is used to plan and control

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!