Question: 5 Pe Applications are scanned in a process with two resources. The first resource has a capacity of 0.74 applications per minute. The capacity of

5 Pe Applications are scanned in a process with

5 Pe Applications are scanned in a process with two resources. The first resource has a capacity of 0.74 applications per minute. The capacity of the second resource is 1.5 applications per minute. The first resource has 1 worker and the second resource has 1 worker. One additional worker is hired who is as productive as the current workers. hom 2 00:04:44 Instruction: Round your answer to three decimal places. What is the new capacity of this process? QI 1.350 applications per n S Ad ADE